Data Center Project – 03-15-19 Weekly Construction Update
Work this week: This week, the construction team began to frame the Data Center building…
Work this week: This week, the construction team began to frame the Data Center building…
Work this week: The construction team completed pouring the slab on grade concrete, and completed the install of the new gas powered generator in the chiller yard…
Monthly status update on all existing Measure L projects.
Work this week: AMG installed the vapor barrier over the grade beams and grids and the completed the underslab-plumbing and electrical work…
Work this week: Early in the week, the construction team continued installing conduit for the building…
Work this week: Due to wet ground conditions, the construction team has postponed recertification of the pad…
Work this week: The construction team installed forms for perimeter curbs and began to pour concrete…
Monthly status update on all existing Measure L projects.
Work this week: Early this week crews installed all the grade beam rebar in preparation for inspection on Wednesday…
Work this week: The general contractor began clearing the grade beam trenches and installing grade rebar…