Data Center Project – 05-31-19 Weekly Construction Update
Work this week: The general contractor made progress on the framing and has completed the structural exterior and interior walls…
Work this week: The general contractor made progress on the framing and has completed the structural exterior and interior walls…
Work this week: The structural exterior and interior walls are now 90% complete…
Work this week: The general contractor is detailing their cold formed metal framing this week…
Work this week: Metal Framing is in process. The contractor has achieved 75% completion on the roof joists and are framing the Data Center’s interior walls…
Monthly status update on all existing Measure L projects.
Work this week: This past week was 100% dedicated to the approval of the roof openings submittal and subsequent to that, roof joist installation (pics 1,2 & 3). Joists are the roof cross “beams” that are the support for everything on the roof…
Work this week: The construction team began installing the new gas line across the north edge of the project…
Monthly status update on all existing Measure L projects.
Work this week: Construction crews continue cold formed metal framing…
Work this week: This week, the construction team began the cold formed metal framing for Data Center…