Aquatics Center and 1000 Complex ADA Upgrades Project – 11-09-18 Weekly Construction Update
Construction crews have completed the competition pool reinforcement and have installed water stops around the drainage piping. Installation of the form for the steps in the teaching pool was completed. Competition-pool surge tank and teaching-pool surge tank reinforcement began. The...
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 11-02-18 Weekly Construction Update
Construction crews are completing the competition pool reinforcement. Installation of the lights in the teaching pool , and the competition pool surge tank framing was completed. Punch list for buildings 1000 & 1300 is being completed.
Download PDF →October 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 10-26-18 Weekly Construction Update
Construction crews completed the majority of the competition pool wall reinforcement. Installation of the lights in the teaching pool began, and excavation of the teaching pool surge tank is complete. Punch list for buildings 1000 & 1300 is near completion.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 10-12-18 Weekly Construction Update
Construction crews installed shotcrete at the pump pit wall and the remainder of the competition pool radius. Installation of the restroom accessories and benches continues in building 1000. Installation of accessories and painting continues in Building 1300 restrooms.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 10-05-18 Weekly Construction Update
Construction crews installed drain rock at the competition pool. Installation of the restroom partitions continues in building 1000. ADA upgrades continue in building 1300 with an installation of plumbing fixtures. Paint prep and priming began in building 1000.
Download PDF →September 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 09-28-18 Weekly Construction Update
Construction crews continue to install forms on the South and West sides of the competition pool along with the pool plumbing. Installation of the restroom partitions continues in building 1000.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 09-21-18 Weekly Construction Update
Work this week: Construction crews completed the demo and over excavation at the south side of the completion pool...
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 09-14-18 Weekly Construction Update
Work this week: Construction crews completed the remainder of the forms at the training pool...
Download PDF →