Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: Upgrades – Aquatic Center

Aquatics Center and 1000 Complex ADA Upgrades Project – 11-09-18 Weekly Construction Update

November 9, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Construction crews have completed the competition pool reinforcement and have installed water stops around the drainage piping. Installation of the form for the steps in the teaching pool was completed. Competition-pool surge tank and teaching-pool surge tank reinforcement began. The...

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 11-02-18 Weekly Construction Update

November 2, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Construction crews are completing the competition pool reinforcement. Installation of the lights in the teaching pool , and the competition pool surge tank framing was completed. Punch list for buildings 1000 & 1300 is being completed.

Download PDF →

October 2018 Monthly Project Update

November 1, 2018 · Construction Updates, SLO 1000 Complex Renovations, SLO Data Center, Technology Upgrades 2nd, Upgrades - Aquatic Center

Monthly status update on all existing Measure L projects.

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 10-26-18 Weekly Construction Update

October 26, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Construction crews completed the majority of the competition pool wall reinforcement. Installation of the lights in the teaching pool began, and excavation of the teaching pool surge tank is complete. Punch list for buildings 1000 & 1300 is near completion.

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 10-12-18 Weekly Construction Update

October 12, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Construction crews installed shotcrete at the pump pit wall and the remainder of the competition pool radius. Installation of the restroom accessories and benches continues in building 1000. Installation of accessories and painting continues in Building 1300 restrooms.

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 10-05-18 Weekly Construction Update

October 5, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Construction crews installed drain rock at the competition pool. Installation of the restroom partitions continues in building 1000. ADA upgrades continue in building 1300 with an installation of plumbing fixtures. Paint prep and priming began in building 1000.

Download PDF →

September 2018 Monthly Project Update

October 1, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Monthly status update on all existing Measure L projects.

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 09-28-18 Weekly Construction Update

September 28, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Construction crews continue to install forms on the South and West sides of the competition pool along with the pool plumbing. Installation of the restroom partitions continues in building 1000.

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 09-21-18 Weekly Construction Update

September 21, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Work this week: Construction crews completed the demo and over excavation at the south side of the completion pool...

Download PDF →

Aquatics Center and 1000 Complex ADA Upgrades Project – 09-14-18 Weekly Construction Update

September 14, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center

Work this week: Construction crews completed the remainder of the forms at the training pool...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: