SLO Instructional Building – 8-05-16 Weekly Construction Update
Work this week: This week’s main focus was completing the final slab-on-grade concrete pour and refining the previously poured sections of the slab...
Download PDF →July 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 7-29-16 Weekly Construction Update
Work this week: This week began with removal the formwork from the completed Slab-on-Grade area...
Download PDF →SLO Instructional Building – 7-22-16 Weekly Construction Update
Work this week: This week included final preparation for the Slab On Grade concrete placement...
Download PDF →SLO Instructional Building – 7-15-16 Weekly Construction Update
Work this week: The concrete contractor completed the vapor barrier, placed the tube steel window supports, and began to place the reinforcing steel for the slab on grade pour scheduled for next week...
Download PDF →June 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 7-08-16 Weekly Construction Update
Work this week: The concrete contractor began installing forms for the slab on grade, vapor barrier and the non-expansive fill below the slab on grade...
Download PDF →SLO Instructional Building – 7-01-16 Weekly Construction Update
Work this week: The structural & site concrete contractor poured over 50 truckloads of concrete for the footings of the building last week...
Download PDF →SLO Instructional Building – 6-24-16 Weekly Construction Update
Work this week: This week was a week of preparation for our concrete pour of the footings on Monday, June 27th...
Download PDF →SLO Instructional Building – 6-17-16 Weekly Construction Update
Work this week: Concrete was poured for the elevator pit walls this week...
Download PDF →