SLO Instructional Building – 6-10-16 Weekly Construction Update
Work this week: Concrete was poured to bottom of footings and the elevator pit floor was placed this week...
Download PDF →May 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 6-03-16 Weekly Construction Update
Work this week: Anchor bolt installation continues along with the installation of reinforcing steel for footings and grade beams for the building...
Download PDF →SLO Instructional Building – 5-27-16 Weekly Construction Update
Work this week: Structural excavations were completed this week...
Download PDF →SLO Instructional Building – 5-20-16 Weekly Construction Update
Work this week: Batter boards were installed and the contractor completed layout of their footings...
Download PDF →April 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 5-13-16 Weekly Construction Update
Work this week: Installation of the site water, sewer, utility lines, and the building pad is complete...
Download PDF →SLO Instructional Building – 5-06-16 Weekly Construction Update
Work this week: The domestic water tie-in to the District’s main service was completed over the weekend...
Download PDF →March 2016 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →SLO Instructional Building – 4-20-16 Weekly Construction Update
Work this week: Excavation for the rerouting of existing water and sewer lines began and continued throughout the week...