NCC Parking Lot 10 & Site Improvements – 03-05-21 Weekly Construction Update
Work this week: Stripping work for the right turn lane leading to the drive aisle entrance was completed. The electrician installed uplights in the planter areas.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-26-21 Weekly Construction Update
Work this week: The contractor placed their second lift of asphalt in the traffic areas.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-19-21 Weekly Construction Update
Work this week: Landscaping contractor began trenching and installing irrigation lines.
Download PDF →Asphalt Resurfacing Phase II – 12-18-20 Weekly Construction Update
Work this week: General contractor installed an asphalt path at Building 7500. The asphalt walkway at Parking Lot 6 was completed. New striping was added to the 5000 Buildings loading dock. Striping work continued at Parking Lot 2.
Download PDF →Asphalt Resurfacing Phase II – 12-04-20 Weekly Construction Update
Work this week: General contractor paved Parking Lot 1 and continued paving Parking Lot 2. Demo began on driveway concrete at Parking Lot 1. Seal coat applied to the basketball court.
Download PDF →November 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Asphalt Resurfacing Phase II – 11-13-20 Weekly Construction Update
Work this week: General contractor began paving Parking Lot 2 and Parking Lot 7. Grading at Parking Lot 1 is complete and ready for the application of class II base.
Download PDF →Asphalt Resurfacing Phase II – 11-06-20 Weekly Construction Update
Work this week: The general contractor applied a seal coat to Education Drive and a section of Parking Lot 2A. Asphalt grinding in Parking Lot 2, Basketball Court and Parking Lot 7 have been completed. Parking Lot 1 is being...
Download PDF →October 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Asphalt Resurfacing Phase II – 10-30-20 Weekly Construction Update
Work this week: The general contractor continued grading work and poured a concrete walkway at Parking Lot 1. Parking lot 2 has been compacted and concrete forms are being installed. Exercise equipment next to the Basketball Courts have been removed.
Download PDF →