North County Campus Parking Lot 10 and Site Improvements – 05-14-21 Weekly Construction Update
Work this week: The contractor finished placing reinforcing steel and form work. Construction team poured concrete for the light pole bases around the future quad area.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 05-07-21 Weekly Construction Update
Work this week: Grading work on the new fire road continued. Drilling & placing rebar cages for the new light pole remains ongoing.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 04-30-21 Weekly Construction Update
Work this week: The contractor completed backfilling of utility trenches. Flagpoles were installed in front of the campus center. Construction team began installation of the pavers in flagpole plaza.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 04-23-21 Weekly Construction Update
Work this week: The contractor completed pressure testing of the chilled water lines and gas line, poured thrust blocks in place, and began backfilling utility trenches.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 04-16-21 Weekly Construction Update
Work this week: The contractor continued with excavation and placement of chilled water lines, and the gas line.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 04-09-21 Weekly Construction Update
Work this week: The surveyor visited the site to locate survey points in the future quad area. Excavation continued for underground utilities.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 04-02-21 Weekly Construction Update
Work this week: The contractor installed the emergency phone and parking pass kiosk. Construction team began installing the bus shelters and continued working on landscaping.
Download PDF →April 2021 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 03-26-21 Weekly Construction Update
Work this week: Contractor continued demolition in the future quad area. The transformer in the quad was demobilized and removed and the chilled water line and gas line point of connection was excavated. The shade structure from the former ECE...
Download PDF →NCC Parking Lot 10 & Site Improvements – 03-12-21 Weekly Construction Update
Work this week: Circuiting was coordinated for the new light poles. Power and Data stations were placed at the locations of the future bus shelters.
Download PDF →