North County Campus Parking Lot 10 and Site Improvements – 07-09-21 Weekly Construction Update
Work this week: Site grading, base placement and compaction, and form work remain ongoing.
Download PDF →North County Campus Parking Lot 10 Asphalt Repairs Phase 2 – 07-02-21 Weekly Construction Update
Work this week: Contractor began pouring concrete for the new curbs and placing conduit and reinforcing steel cages for new site lighting.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-25-21 Weekly Construction Update
Work this week: The contractor continued setting formwork, reinforcing steel, and poured additional flatwork in the courtyard area. The electrician began setting light poles on the concrete bases.
Download PDF →North County Campus Parking Lot 10 Asphalt Repairs Phase 2 – 06-25-21 Weekly Construction Update
Work this week: The contractor continued with demolition work. Construction team began excavating for curb and gutter and setting formwork.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-18-21 Weekly Construction Update
Work this week: The contractor continued site grading and the first concrete pour was completed for the new walkways in the campus quad area.
Download PDF →North County Campus Parking Lot 10 Asphalt Repairs Phase 2 – 06-18-21 Weekly Construction Update
Work this week: The contractor began demolition.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-11-21 Weekly Construction Update
Work this week: The contractor started base placement and compaction work, along with formwork and reinforcing steel placement for the new walkways in the courtyard. Concrete is scheduled to follow. Rough grading of the site is ongoing.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-04-21 Weekly Construction Update
Work this week: Conduit trenching for site lighting, electrical, and rough grading of the site are ongoing. The surveyor made an onsite visit to shoot points and elevations in preparation for formwork.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 05-28-21 Weekly Construction Update
Work this week: Contractor continued trenching work for conduit runs for site lighting, and rough grading of the site.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 05-21-21 Weekly Construction Update
Work this week: The contractor continued work on rough grading of the site and placed the remaining light poles at the front entrance of the campus center.
Download PDF →