Asphalt Resurfacing Phase II – 10-23-20 Weekly Construction Update
Work this week: The general contractor continued demo on existing driveways at parking lot 2 along with a section of damaged asphalt. Sidewalk ramps have been demoed and concrete forms and rebar set in place. Excavation and grading remain ongoing...
Download PDF →September 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →August 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →July 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →District Wide Asphalt – 07-31-20 Weekly Construction Update
Work this week: Romauldo, Hollister, Cuesta College, and Chorro Valley Roads have received slurry seal.
Download PDF →District Wide Asphalt – 07-24-20 Weekly Construction Update
Work this week: Parking lot striping and seal coat for parking lot 5A remain are currently on-going.
Download PDF →District Wide Asphalt – 07-17-20 Weekly Construction Update
Work this week: All parking lot paving is complete. Some concrete collars are being installed around various manhole covers.
Download PDF →District Wide Asphalt – 07-10-20 Weekly Construction Update
Work this week: Parking lot 6 in front of the tennis courts has been rebuilt and paved. The service road, loading dock area, and two pedestrian pathways along the service road have also been paved.
Download PDF →District Wide Asphalt – 07-03-20 Weekly Construction Update
Work this week: The repaving work at the entrance/exit road of Romauldo rd. has been completed. Contractor continued excavation and compaction at parking lot 6. Work on the pedestrian walkways off the service road has begun.
Download PDF →District Wide Asphalt – 06-26-20 Weekly Construction Update
Work this week: Paving work at Parking lot 5 and the 4000’s parking lot has been completed.
Download PDF →