Data Center Project – 01-14-19 Weekly Construction Update
Work this week: Rain and subsequent wet conditions continued…
Work this week: Rain and subsequent wet conditions continued…
Work this week: Weather has slowed progress this week. The electrical contractor preformed preliminary work in the “chiller yard” preparing communication and electrical tie-ins and installing conduits for the new backup generator (lower left pic)…
Work this week: Construction crews resumed the installation and backfilling of the new sewer line and are exporting the spoils…
Monthly status update on all existing Measure L projects.
Work this week: Construction crews the under slab work and are prepping for grade beam install, and includes the installation of rebar, then the pouring of the concrete…
Work this week: Construction crews started laying out and trenching for the under slab (foundation) sewer piping…
Work this week: Weather slowed progress of the site work, however, construction crews were able to open and inspect current condition and determine tie-in areas for the new utilities and are able to move forward…
Monthly status update on all existing Measure L projects.
Work this week: The construction team resumed the install and backfill of utility conduits and trenching, and also the survey and layout of the building…
Construction crews began drilling and the installation of Data Center’s concrete piers (caissons)..