Aquatics Center and 1000 Complex ADA Upgrades Project – 08-31-18 Weekly Construction Update
Work this week: The project’s construction team completed the majority of the foam install at the training pool…
Work this week: The project’s construction team completed the majority of the foam install at the training pool…
Work this week: The project’s construction team completed the majority of the foam install at the training pool…
Work this week: The installation of aggregate base in the competition pool was completed…
Work this week: Construction crews continue the installation of aggregate base to backfill the Competition Pool from bedrock to the bottom of drain rock elevation…
Work this week: Construction crews completed the majority of the excavation and hauled off soils from the Competition pool…
Work this week: Construction personnel continue the excavation, removal and off-haul of soil from the competition pool…
Work this week: Construction personnel continued the excavation and removal of soil from the competition pool and are excavating the trenches for subfloor drainage piping at the new teaching pool…
Work this week: Construction personnel continued with demo, excavation, and removal soil from the competition pool and excavated the pipe trenches for subfloor drainage piping at the new teaching pool..
Work this week: Construction of the new Aquatics Center began on 05/21/18…
Work this week: Construction of the new Aquatics Center started on 05/21/18…