Aquatics Center and 1000 Complex ADA Upgrades Project – 01-11-19 Weekly Construction Update
Work this week: Construction crews are continuing to backfill behind the competition pool walls…
Work this week: Construction crews are continuing to backfill behind the competition pool walls…
Work this week: Construction crews are continuing to backfilll behind the competition pool and teach pool walls…
Monthly status update on all existing Measure L projects.
Work this week: Construction crews began backfilling behind the competition pool walls…
Work this week: Construction crews completed the removal of forms at the competition pool and teach pool walls…
Work this week: Construction crews have completed the placement of Shotcrete at the competition pool and teach pool walls…
Work this week: Construction crews have completed the placement of Shotcrete at the competition pool and teach pool surge tanks…
Monthly status update on all existing Measure L projects.
Work this week: Construction crews have completed the demolition of the concrete stairs and walk way at building 1100…
Construction crews have completed the competition pool concrete floor placement…