Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: SLO Campus Instructional Building

SLO Instructional Building – 09-28-17 Weekly Construction Update

September 28, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: Plumbing finishes were installed in the first-floor bathrooms while the installation of the ceramic tile continued in the second-floor bathrooms...

Download PDF →

SLO Instructional Building – 09-22-17 Weekly Construction Update

September 22, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The site exterior has continued to be graded...

Download PDF →

SLO Instructional Building – 09-15-17 Weekly Construction Update

September 15, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The exterior doors on the first floor were painted and are ready to be installed next week. Site grading has begun around the building...

Download PDF →

SLO Instructional Building – 09-08-17 Weekly Construction Update

September 8, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The floors in the first-floor restroom were floated and in preparation for tile to be set next week...

Download PDF →

SLO Instructional Building – 09-01-17 Weekly Construction Update

September 1, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The installation of the handrail on the exteriors stairs was completed...

Download PDF →

August 2017 Monthly Project Update

September 1, 2017 · Construction Updates, North County Campus Center, SLO Campus Instructional Building

Monthly status update on all existing Measure L projects.

Download PDF →

SLO Instructional Building – 08-25-17 Weekly Construction Update

August 25, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The plaster installation was completed this week, and the sheet metal contractor is installing the downspouts on the exterior of the building...

Download PDF →

SLO Instructional Building – 08-18-17 Weekly Construction Update

August 18, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The plaster contractor has begun to apply the finish coat of the plaster system to the exterior of the building...

Download PDF →

SLO Instructional Building – 08-11-17 Weekly Construction Update

August 11, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The lath and plaster contractor is on site installing caulking where the plaster meets the steel beams, and the acoustical ceiling grid has begun to be installed in the classrooms on the first floor...

Download PDF →

SLO Instructional Building – 08-04-17 Weekly Construction Update

August 4, 2017 · Construction Updates, SLO Campus Instructional Building

Work this week: The plaster installation was completed this week and has a week of cure time before the finish can be applied...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: