1000 Complex Roof/HVAC Replacement – 07-20-18 Weekly Construction Update
Work this week: The roofing contractor completed installing the new roof on building 1300 this week...
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 07-20-18 Weekly Construction Update
Work this week: Construction personnel continue the excavation, removal and off-haul of soil from the competition pool...
Download PDF →1000 Complex Roof/HVAC Replacement – 07-13-18 Weekly Construction Update
Work this week: The mechanical contractor has modified the existing roof curbs, extended all the roof vents, and installed the new condensate, roof hatch, and drains...
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 07-13-18 Weekly Construction Update
Work this week: Construction personnel continued the excavation and removal of soil from the competition pool and are excavating the trenches for subfloor drainage piping at the new teaching pool...
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 07-06-18 Weekly Construction Update
Work this week: Construction personnel continued with demo, excavation, and removal soil from the competition pool and excavated the pipe trenches for subfloor drainage piping at the new teaching pool..
Download PDF →June 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 06-29-18 Weekly Construction Update
Work this week: Construction of the new Aquatics Center began on 05/21/18...
Download PDF →1000 Complex Roof/HVAC Replacement – 06-15-18 Weekly Construction Update
Work this week: The electrical contractor has disconnected the power, fire alarm, and exhaust fan feeders from the HVAC units...
Download PDF →