North County Campus IT Backup Generator – 06-18-21 Weekly Construction Updates
Work this week: The contractor installed the emergency stop button on the MTS and the gas regulator.
Download PDF →North County Campus IT Backup Generator – 05-28-21 Weekly Construction Updates
Work this week: The wiring work for the manual and automatic transfer switches has been completed. Generator was received and set it in place.
Download PDF →North County Campus IT Backup Generator – 05-21-21 Weekly Construction Updates
Work this week: The contractor set the automatic transfer switch, and the manual transfer switch, and began pulling wiring through the previously installed conduits.
Download PDF →April 2021 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus IT Backup Generator – 03-19-21 Weekly Construction Updates
Work this week: Conduit boxes were placed and conduit was ran above ceiling from the electrical room to the server room. The contractor began work on the gas feed for the generator.
Download PDF →NCC IT Backup Generator – 03-12-21 Weekly Update
Work this week: Contractor completed conduit runs. Concrete was replaced at the walkway and poured at the generator pad in the chiller yard.
Download PDF →District-Wide Upgrades – Primary Electrical – 01-10-20 Weekly Construction Update
Work this week: General contractor installed all new electrical primary gear...
Download PDF →September 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →August 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →District-Wide Upgrades – Primary Electrical – 08-30-19 Weekly Construction Update
Work This Week: The contractor completed the campus wide shut down allowing them to do the coring needed to get their conduits into the vaults...
Download PDF →