Faculty Interim Housing – 1-11-16 Weekly Construction Update
Work this week: Electrical and fire alarm work is substantially complete…
Work this week: Electrical and fire alarm work is substantially complete…
Work this week: Modulars have been delivered and set…
Work this week: Completion of punch list items. Owner move-in continues to progress…
Work this week: Roof demolition complete. Installation of new single ply roof begins this week…
Work this week: Completion of punch list items. Owner move-in continues to progress…
Work this week: Completing interior finishes and dropping ceiling tiles…
Work this week: Electrical and low-voltage work continues, with fire alarm devices installed…
Work this week: All portables have been delivered. Electrical and low-voltage work continues to progress…
Work this week: Finish setting and installing portables with ongoing electrical and low-voltage work…