SLO Instructional Building – 02-03-17 Weekly Construction Update
Work this week: The metal framer began to place interior walls on the first floor…
Work this week: The metal framer began to place interior walls on the first floor…
Work this week: The metal framing contractor continued their placement of the second floor exterior infill…
Work this week: The concrete contractor placed the last portion of the second floor deck…
Work this week: The metal framing contractor began to weld the second floor track to the tube steel frames and continued to frame the exterior infills…
Work this week: The concrete contractor has placed roughly 65% of the second floor slab…
Work this week: Rebar has been installed on the second floor deck, and the lighting in the cantilevered slab has been roughed in…
Work this week: The mansard decking has been completed…
Work this week: The mansard decking is currently approximately 90% complete…
Work this week: The mansard decking is approximately 25% complete…
Work this week: The mansard decking is roughly 25% complete…