Data Center Project – 11-08-19 Weekly Construction Update
Work this week: General contractor is working on punch list items…
Work this week: General contractor is working on punch list items…
Work this week: The general contractor continued pulling fiber from the new Data Center to various buildings around campus…
Monthly status update on all existing Measure L projects.
Work this week: The general contractor is continuing work on the HVAC controls and fire suppression/alarm system…
Work this week: The general contractor continued work on the HVAC controls, joint sealant, and door hardware on interior of the building…
Work this week: The Data Center’s general contractor began installing the HVAC controls, joint sealant and door hardware on the interior of the building…
Monthly status update on all existing Measure L projects.
Monthly status update on all existing Measure L projects.
Work This Week: The exterior of the Data Center has received its last coat of paint and the tile roofing is in progress…
Work This Week: The contractor has completed the brown coat; which is the second coat of three…