Technology Upgrades Project – 2000 Complex – 10-18-19 Weekly Construction Update
Work this week: The general contractor completed the installation of the exterior conduit and box at Building 2000…
Work this week: The general contractor completed the installation of the exterior conduit and box at Building 2000…
Work this week: The construction team continued the installation of the heating and air conditioning units on Building 2300 and began to install the accessory curbs…
Work this week: The construction team has completed the ADA improvements to the restrooms at Building 2200 and began installation of exterior drinking fountains. Progress has been made with the restrooms at Building 2300. The
Work this week: The construction team has removed the existing heating and air conditioning equipment from Building 2300…
Work this week: The general contractor completed the underground electrical work from the Data Center vaults to Building 2200…
Monthly status update on all existing Measure L projects.
Work this week: The construction team continued installation of the roof membrane…
Monthly status update on all existing Measure L projects.
Work This Week: Construction crews have completed the Wireless and TR Upgrades Project…
Work This Week: Construction crews have completed demolition of the 2400 roof and began demolition of the 2100 roof…