SLO Campus Center – 09-15-23 Weekly Construction Update

This week, the contractor started forming building perimeter walls on the west 1/3 of the building. Electrical contractor continued installation of under slab electrical conduit. Elevator Pit drain line & backfill was completed.

Site utility contractor continued installation of site storm drain utility, and backfilling of site electrical trench from the POC into the building.