SLO Campus Center – 09-08-23 Weekly Construction Update

The contractor poured half of the building pad footings and tie-beam footings. Excavation has started on the 2nd half of the building pad footings and tie-beam footings. Elevator pit wall waterproofing was installed.

Site utility contractor continued installation of site storm drain utility, and installation of site electrical conduit from the POC into the building.