SLO Campus Center – 09-08-23 Weekly Construction Update
September 11, 2023 · SLO Campus Center
The contractor poured half of the building pad footings and tie-beam footings. Excavation has started on the 2nd half of the building pad footings and tie-beam footings. Elevator pit wall waterproofing was installed.
Site utility contractor continued installation of site storm drain utility, and installation of site electrical conduit from the POC into the building.
Download PDF →