SLO Campus Center – 09-01-23 Weekly Construction Update
September 5, 2023 · SLO Campus Center
The contractor began excavation of the building pad footings and tie-beam footings. Site utility contractor continued installation of site storm drain utility, gas service, and started under slab electrical conduit installation.