SLO Campus Center – 07-14-23 Weekly Construction Update

Work this week: This week, the contractor has started excavating the building grade beams,
installed the building fire riser piping, and brought the 12kv high voltage electrical conduit into the
building perimeter.

Concrete form work and rebar installation continues on the elevator pit walls.

Contractor completed installation of the site domestic water lines, wrapped the joints, poured
the concrete thrust blocks, and has started backfilling the site waterline trenches.