SLO Campus Center – 06-30-23 Weekly Construction Update
June 30, 2023 · SLO Campus Center
Work this week: The contractor continued backfilling the under-slab plumbing trenches. Elevator pit rebar was installed; pit floor and footings have been poured. Contractor will begin forming elevator pit walls next week.
Trenching and installation of site domestic water and fire water line is in progress.