SLO Campus Center – 06-30-23 Weekly Construction Update

Work this week: The contractor continued backfilling the under-slab plumbing trenches. Elevator pit rebar was installed; pit floor and footings have been poured. Contractor will begin forming elevator pit walls next week.

Trenching and installation of site domestic water and fire water line is in progress.

Download PDF →