Buildings 4000-7000 Wireless and TR Upgrades – 01-29-20 Weekly Construction Update
Work this week: Contractor has completed the telecommunication upgrades in Building 7100N, 6200, and 4400. New fiber cable was pulled to Buildings 4500, 4600, and 5300.
Download PDF →Buildings 4000-7000 Wireless and TR Upgrades – 12-18-20 Weekly Construction Update
Work this week: Contractor installed new cable and raceways in Buildings 4200, 4400, 4600 and pulled new cable along the hallway of Building 4300. New data cabinets have been installed in building 6100 and 6300 as they work to complete...
Download PDF →Buildings 4000-7000 Wireless and TR Upgrades – 12-04-20 Weekly Construction Update
Work this week: Contractor is working on Building 6100 and 6300 removing existing network cables and installing new Cat6A cable, along with new raceways and outlets. Work in Building 5100 & 5300 also began.
Download PDF →January 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →Technology Upgrades Project – Fiber Star – 10-25-19 Weekly Construction Update
Work this week: The general contractor completed the overhead conduit run in Building 9100...
Download PDF →Technology Upgrades Project – 2000 Complex – 10-18-19 Weekly Construction Update
Work this week: The general contractor completed the installation of the exterior conduit and box at Building 2000...
Download PDF →Technology Upgrades Project – 2000 Complex – 10-11-19 Weekly Construction Update
Work this week: The general contractor completed the underground electrical work from the Data Center vaults to Building 2200...
Download PDF →September 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →August 2019 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →2000 Complex Renovations Project – 08-16-19 Weekly Construction Update
Work This Week: Construction crews have completed the Wireless and TR Upgrades Project...
Download PDF →