Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: SLO Switchgear Replacement

SLO Electrical Building Switchgear Replacement – 12-16-22 Weekly Construction Update

December 16, 2022 · SLO Switchgear Replacement

Work this week: Contractor demolished a portion of the north facing wall which did not have adequate grout penetration. That portion has been reconstructed and framing is scheduled to begin on Monday. Temporary transformer and pad have also been set...

Download PDF →

SLO Electrical Building Switchgear Replacement – 12-9-22 Weekly Construction Update

December 9, 2022 · SLO Switchgear Replacement

Work this week: Contractor poured concrete slab. However, core samples revealed inadequate grout penetration of block cells. Contractor has been instructed by structural engineer to demo a portion of the north facing wall.

Download PDF →

SLO Electrical Building Switchgear Replacement – 12-2-22 Weekly Construction Update

December 2, 2022 · SLO Switchgear Replacement

Work this week: Contractor grouted previously installed courses of block and continued erecting remaining courses. Mixer is on site today to pour grout in the last courses of block.

Download PDF →

November Monthly Project Updates

November 30, 2022 · District Wide Upgrades 2nd, SLO Switchgear Replacement

Monthly status update.

Download PDF →

SLO Electrical Building Switchgear Replacement – 11-25-22 Weekly Construction Update

November 25, 2022 · SLO Switchgear Replacement

Work this week: Contractor continued erecting block walls at 6300.

Download PDF →

SLO Electrical Building Switchgear Replacement – 11-18-22 Weekly Construction Update

November 18, 2022 · SLO Switchgear Replacement

Work this week: Contractor began erecting block walls and installed double door frame. Trenches were backfilled at walkways and asphalt paving work has been completed.

Download PDF →

SLO Electrical Building Switchgear Replacement – 11-11-22 Weekly Construction Update

November 11, 2022 · SLO Switchgear Replacement

Work this week: Contractor installed electrical vaults and began installing the associated conduits. They have also started backfilling where a section of the existing sewer was replaced.

Download PDF →

SLO Electrical Building Switchgear Replacement – 11-4-22 Weekly Construction Update

November 4, 2022 · SLO Switchgear Replacement

Work this week: Contractor performed trenching work in preparation to run conduits from switchgear pad at 6300 to UG conduits located at 6200.

Download PDF →

SLO Electrical Building Switchgear Replacement – 10-26-22 Weekly Construction Update

October 26, 2022 · SLO Switchgear Replacement

Work this week: Contractor poured concrete footings at 6300 and cut CMU block in preparation to lay first courses. Construction team is prepared to lay first block courses so they can start preparing to pour the concrete slab.

Download PDF →

September Monthly Project Updates

September 30, 2022 · District Wide Upgrades 2nd, SLO Switchgear Replacement, Technology Upgrades 3rd

Monthly status update.

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: