October 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →1000s Complex TR & Wireless Upgrades -10-26-18
The construction team installed new IDF racks, pulled new cabling from AP’s, and data drops to new IDF racks; and began terminating data in IDF racks and data drops.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 10-26-18 Weekly Construction Update
Construction crews completed the majority of the competition pool wall reinforcement. Installation of the lights in the teaching pool began, and excavation of the teaching pool surge tank is complete. Punch list for buildings 1000 & 1300 is near completion.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 10-12-18 Weekly Construction Update
Construction crews installed shotcrete at the pump pit wall and the remainder of the competition pool radius. Installation of the restroom accessories and benches continues in building 1000. Installation of accessories and painting continues in Building 1300 restrooms.
Download PDF →1000 Complex Roof/HVAC Replacement – 10-05-18 Weekly Construction Update
Controls for the mechanical equipment is complete, and the final electrical connections to mechanical equipment was complete this week. Condensate lines were hooked up to condensers and charged. Scheduled start-up is 10/9/18.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 10-05-18 Weekly Construction Update
Construction crews installed drain rock at the competition pool. Installation of the restroom partitions continues in building 1000. ADA upgrades continue in building 1300 with an installation of plumbing fixtures. Paint prep and priming began in building 1000.
Download PDF →September 2018 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →1000 Complex Roof/HVAC Replacement – 9-29-18 Weekly Construction Update
Installation of the controls for the mechanical equipment is ongoing, and the team began installing T-stats in buildings 1000 and 1300. Startup is scheduled for 10/9/18. The temporary fencing has been removed from around buildings 1000 and 1300.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 09-28-18 Weekly Construction Update
Construction crews continue to install forms on the South and West sides of the competition pool along with the pool plumbing. Installation of the restroom partitions continues in building 1000.
Download PDF →Aquatics Center and 1000 Complex ADA Upgrades Project – 09-21-18 Weekly Construction Update
Work this week: Construction crews completed the demo and over excavation at the south side of the completion pool...
Download PDF →