NCC Parking Lot 10 & Site Improvements – 12-18-20 Weekly Construction Update
Work this week: Concrete was poured in the bus drop-off area, curbs were poured on the east end of Parking Lot 10, and light pole bases around the site were put into place.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-11-20 Weekly Construction Update
Work this week: Rough grading, and formwork remains ongoing. Additional gutters were poured.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-04-20 Weekly Construction Update
Work this week: Aggregate base compaction continued, curb and gutter as well as flatwork were put into place, CMU monument signage was grouted, and the existing parking ticket dispenser was removed to be replaced with a new unit in the...
Download PDF →November 2020 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →NCC Parking Lot 10 & Site Improvements – 11-27-20 Weekly Construction Update
Work this week: Aggregate base compaction continued in traffic areas, and CMU entrance walls were constructed at the entrance of Parking Lot 10.
Download PDF →NCC Parking Lot 10 & Site Improvements – 11-20-20 Weekly Construction Update
Work this week: Installation of site lighting continued, with conduit being run and reinforcing steel being placed for the light pole bases. A large portion of the curb and gutter was poured at the drive aisle entry and the drop...
Download PDF →NCC Parking Lot 10 & Site Improvements – 11-13-20 Weekly Construction Update
Work this week: Additional base was placed throughout Parking Lot 10. Grading base & Site lighting installation is ongoing.
Download PDF →NCC Parking Lot 10 & Site Improvements – 11-06-20 Weekly Construction Update
Work this week: Contractor placed additional form work throughout Parking Lot 10. Construction team began laying base in the drive aisle to prepare for asphalt paving work. Irrigation has been tied into the main line and site lighting installation is...
Download PDF →NCC Parking Lot 10 & Site Improvements – 10-30-20 Weekly Construction Update
Work this week: Formwork at the front entry is in place and curb and gutter is scheduled to take place next week.
Download PDF →NCC Parking Lot 10 & Site Improvements – 10-23-20 Weekly Construction Update
Work this week: Contractor continued working on site electrical work and irrigation line installation. Demolition of existing curb and asphalt sidewalk on the east end of Parking Lot 10 was completed. Curb and gutter installation began.
Download PDF →