2400 & 2800 TR Renovation – 07-28-23 Weekly Construction Update
July 28, 2023 · Technology Upgrades 3rd
Work this week: The contractor has tested 70% of all fiberoptic cables pulled into N2400. Labeling is 99% complete, and there are 120 remaining cables to be landed in the IDF room.