4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-18-22 Weekly Construction Update

Work this week: Contractor hung drywall lids and installed lath system at Building 6100. Plumbing fixtures have been installed in 4100 and toilet partitions are in progress. Demolition work at Building 4300 has been completed and underground plumbing work remains ongoing.