SLO Instructional Building – 08-04-17 Weekly Construction Update
Work this week: The plaster installation was completed this week and has a week of cure time before the finish can be applied…
Work this week: The plaster installation was completed this week and has a week of cure time before the finish can be applied…
Monthly status update on all existing Measure L projects.
Work this week: The plaster has begun to be installed on the exterior of the building…
Work this week: The electrician is working on the conduit at the first floor cable trays, as well as bringing conduit to the light fixtures in the soffits on the second floor…
Work this week: Taping of the second floor walls continues as walls have been insulated and drywall placed…
Work this week: The electrical contractor has begun to install their cable tray within the first floor ceiling and is continuing with their second floor rough in…
Monthly status update on all existing Measure L projects.
Work this week: The air conditioning units were hoisted and set on the roof by a crane on Wednesday…
Work this week: The second floor exterior windows have continued to be installed…
Work this week: The elevator doors have been set which will allow for the remaining exterior walls to be closed in…