SLO Electrical Building Switchgear Replacement – 02-17-23 Weekly Construction Update
February 17, 2023 · SLO Switchgear Replacement
Work this week: Roof framing is on hold pending arrival of new 4×6” nailers, which should be here this week. NCM is currently laying base in preparation for concrete flatwork which will be poured this week.