SLO Electrical Building Switchgear Replacement – 12-9-22 Weekly Construction Update
December 9, 2022 · SLO Switchgear Replacement
Work this week: Contractor poured concrete slab. However, core samples revealed inadequate grout penetration of block cells. Contractor has been instructed by structural engineer to demo a portion of the north facing wall.