SLO Electrical Building Switchgear Replacement – 12-16-22 Weekly Construction Update
December 16, 2022 · SLO Switchgear Replacement
Work this week: Contractor demolished a portion of the north facing wall which did not have adequate grout penetration. That portion has been reconstructed and framing is scheduled to begin on Monday. Temporary transformer and pad have also been set in place.