SLO 6100, 6300, and 7100 Roofing and HVAC – 11-19-21 Weekly Construction Update
November 19, 2021 · SLO HVAC/Roofs Phase 2
Work this week: Ductwork for the new HVAC system is being installed on the main roof of Building 6300 and the installation of sheet metal caps on the parapet walls commenced.