SLO 6100, 6300, and 7100 Roofing and HVAC – 11-12-21 Weekly Construction Update
November 12, 2021 · SLO HVAC/Roofs Phase 2
Work this week: Contractor completed reframing of parapet walls as well as the roofing on the main roof. Demolition of smaller roof wells has begun.
Download PDF →