Restroom/Drinking Fountain ADA Upgrades – 04-01-22 Weekly Construction Update
April 1, 2022 · District Wide Upgrades 2nd
Work this week: Contractor mobilized and began demolition in Buildings 4000, 1400 and 7100. MEP rough in work began in Building 4000 and 1400.