North County Campus Parking Lot 10 and Site Improvements – 06-11-21 Weekly Construction Update
June 11, 2021 · District Wide Asphalt, North County Sitework
Work this week: The contractor started base placement and compaction work, along with formwork and reinforcing steel placement for the new walkways in the courtyard. Concrete is scheduled to follow. Rough grading of the site is ongoing.