North County Campus Parking Lot 10 and Site Improvements – 04-23-21 Weekly Construction Update
April 23, 2021 · District Wide Asphalt, North County Sitework
Work this week: The contractor completed pressure testing of the chilled water lines and gas line, poured thrust blocks in place, and began backfilling utility trenches.