NCC Parking Lot 10 & Site Improvements – 02-26-21 Weekly Construction Update
Work this week: The contractor placed their second lift of asphalt in the traffic areas.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-19-21 Weekly Construction Update
Work this week: Landscaping contractor began trenching and installing irrigation lines.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-05-21 Weekly Construction Update
Work this week: New pedestrian flat work was poured at the walkway connecting Parking Lot 10 to the Campus Center. The second lift of asphalt paving is scheduled for next week.
Download PDF →February 2021 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-22-21 Weekly Construction Update
Work this week: New concrete was poured at the front of the Campus Center. Additional concrete was poured at the front drive aisle entrance off Buena Vista Drive.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-15-21 Weekly Construction Update
Work this week: New concrete was poured at the front of the Campus Center. New curb, gutter, and accessible pathways were also poured at the entrance to Parking Lot 11.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-08-21 Weekly Construction Update
Work this week: The first lift of asphalt was placed in Parking Lot 10. Additional concrete was poured around the Parking Lot.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-18-20 Weekly Construction Update
Work this week: Concrete was poured in the bus drop-off area, curbs were poured on the east end of Parking Lot 10, and light pole bases around the site were put into place.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-11-20 Weekly Construction Update
Work this week: Rough grading, and formwork remains ongoing. Additional gutters were poured.
Download PDF →NCC Parking Lot 10 & Site Improvements – 12-04-20 Weekly Construction Update
Work this week: Aggregate base compaction continued, curb and gutter as well as flatwork were put into place, CMU monument signage was grouted, and the existing parking ticket dispenser was removed to be replaced with a new unit in the...
Download PDF →