Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: North County Sitework

NCC Parking Lot 10 & Site Improvements – 02-26-21 Weekly Construction Update

February 26, 2021 · District Wide Asphalt, NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: The contractor placed their second lift of asphalt in the traffic areas.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 02-19-21 Weekly Construction Update

February 19, 2021 · District Wide Asphalt, NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: Landscaping contractor began trenching and installing irrigation lines.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 02-05-21 Weekly Construction Update

February 5, 2021 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: New pedestrian flat work was poured at the walkway connecting Parking Lot 10 to the Campus Center. The second lift of asphalt paving is scheduled for next week.

Download PDF →

February 2021 Monthly Project Update

February 1, 2021 · NCC Early Childhood Education Center, NCC Parking Lot 10 and Monument Sign, North County Sitework, SLO HVAC/Roofs Phase 1

Monthly status update on all existing Measure L projects.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 01-22-21 Weekly Construction Update

January 22, 2021 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: New concrete was poured at the front of the Campus Center. Additional concrete was poured at the front drive aisle entrance off Buena Vista Drive.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 01-15-21 Weekly Construction Update

January 15, 2021 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: New concrete was poured at the front of the Campus Center. New curb, gutter, and accessible pathways were also poured at the entrance to Parking Lot 11.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 01-08-21 Weekly Construction Update

January 8, 2021 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: The first lift of asphalt was placed in Parking Lot 10. Additional concrete was poured around the Parking Lot.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 12-18-20 Weekly Construction Update

December 18, 2020 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: Concrete was poured in the bus drop-off area, curbs were poured on the east end of Parking Lot 10, and light pole bases around the site were put into place.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 12-11-20 Weekly Construction Update

December 11, 2020 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: Rough grading, and formwork remains ongoing. Additional gutters were poured.

Download PDF →

NCC Parking Lot 10 & Site Improvements – 12-04-20 Weekly Construction Update

December 4, 2020 · NCC Parking Lot 10 and Monument Sign, North County Sitework

Work this week: Aggregate base compaction continued, curb and gutter as well as flatwork were put into place, CMU monument signage was grouted, and the existing parking ticket dispenser was removed to be replaced with a new unit in the...

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Center Design
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: