Cuesta College Bond Info

  • About Measure L
    • General Info
    • Ballot Language
    • Frequently Asked Questions
  • Project Info
    • Project Overview
    • Projects: 1st Issuance
    • Projects: 2nd Issuance
    • Projects: 3rd Issuance
    • Projects: 4th Issuance
    • Featured Image Gallery
    • Construction Alerts
    • SLO Campus Map
    • North County Map
  • Oversight Committee
  • Business Opportunities
    • Contractor Prequalification
    • Business RFQs/RFPs
    • Bid Timelines
    • Online Plan Room
  • News
  • Contact

Category: North County Sitework

North County Campus Parking Lot 10 and Site Improvements – 08-6-21 Weekly Construction Update

August 6, 2021 · District Wide Asphalt, North County Sitework

 Work this week: The contractor excavated and placed rock and fabric in the dry creek area, additional concrete for the main quad area walkway was poured, and power charging stations were set in place. 

Download PDF →

July 2021 Monthly Project Update

July 31, 2021 · District Wide Asphalt, North County Sitework

Monthly status update on all existing Measure L projects.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 07-30-21 Weekly Construction Update

July 30, 2021 · District Wide Asphalt, North County Sitework

Work this week: The contractor set additional form work and placed reinforcing steel in preparation for the next concrete pour. Trenching work for irrigation lines and fine grading is currently ongoing.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 07-23-21 Weekly Construction Update

July 23, 2021 · District Wide Asphalt, North County Sitework

Work this week: Additional formwork and reinforcing steel were placed and concrete was poured in the new quad/courtyard.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 07-16-21 Weekly Construction Update

July 16, 2021 · District Wide Asphalt, North County Sitework

Work this week: Additional formwork and reinforcing steel were placed. Concrete was poured for the new walkways and planters. Base placement and compaction work remain ongoing to prepare for additional concrete.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 07-09-21 Weekly Construction Update

July 9, 2021 · District Wide Asphalt, North County Sitework

Work this week: Site grading, base placement and compaction, and form work remain ongoing.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 07-02-21 Weekly Construction Update

July 2, 2021 · North County Sitework

Work this week: Contractor continued site grading. Electrician installed heads on the light poles.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 06-25-21 Weekly Construction Update

June 25, 2021 · District Wide Asphalt, North County Sitework

Work this week: The contractor continued setting formwork, reinforcing steel, and poured additional flatwork in the courtyard area. The electrician began setting light poles on the concrete bases.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 06-18-21 Weekly Construction Update

June 18, 2021 · District Wide Asphalt, North County Sitework

Work this week: The contractor continued site grading and the first concrete pour was completed for the new walkways in the campus quad area.

Download PDF →

North County Campus Parking Lot 10 and Site Improvements – 06-11-21 Weekly Construction Update

June 11, 2021 · District Wide Asphalt, North County Sitework

Work this week: The contractor started base placement and compaction work, along with formwork and reinforcing steel placement for the new walkways in the courtyard. Concrete is scheduled to follow. Rough grading of the site is ongoing.

Download PDF →
← Newer Posts
Older Posts →
  • Search News:

    Search the Cuesta College Bond Website:
  • News Categories

    • Articles
    • Construction Updates
      • 9100 Roofing-HVAC
      • District Wide Asphalt
      • District Wide Upgrades
      • District Wide Upgrades 2nd
      • District-Wide Wayfinding
      • EV Charging Stations
      • Hollister Adobe Stabilization
      • Interim Housing
      • NCC Campus-wide
      • NCC Early Childhood Education Center
      • NCC Parking Lot 10 and Monument Sign
      • North County Campus Center
      • North County Sitework
      • Planning – Aquatic Center
      • Repairs – HVAC/Roofs 1100, 4500, and 4600
      • SLO 1000 Complex Renovations
      • SLO 2000 Complex Renovations
      • SLO Campus Center
      • SLO Campus Instructional Building
      • SLO Data Center
      • SLO HVAC/Roofs Phase 1
      • SLO HVAC/Roofs Phase 2
      • SLO Switchgear Replacement
      • Technology Upgrades 2nd
      • Technology Upgrades 3rd
      • Upgrades – Aquatic Center
    • Press Releases
    • Uncategorized

Back To Top

Cuesta College Logo
Search the Cuesta College Bond Website: