North County Campus Parking Lot 10 and Site Improvements – 08-6-21 Weekly Construction Update
Work this week: The contractor excavated and placed rock and fabric in the dry creek area, additional concrete for the main quad area walkway was poured, and power charging stations were set in place.
Download PDF →July 2021 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 07-30-21 Weekly Construction Update
Work this week: The contractor set additional form work and placed reinforcing steel in preparation for the next concrete pour. Trenching work for irrigation lines and fine grading is currently ongoing.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 07-23-21 Weekly Construction Update
Work this week: Additional formwork and reinforcing steel were placed and concrete was poured in the new quad/courtyard.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 07-16-21 Weekly Construction Update
Work this week: Additional formwork and reinforcing steel were placed. Concrete was poured for the new walkways and planters. Base placement and compaction work remain ongoing to prepare for additional concrete.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 07-09-21 Weekly Construction Update
Work this week: Site grading, base placement and compaction, and form work remain ongoing.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 07-02-21 Weekly Construction Update
Work this week: Contractor continued site grading. Electrician installed heads on the light poles.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-25-21 Weekly Construction Update
Work this week: The contractor continued setting formwork, reinforcing steel, and poured additional flatwork in the courtyard area. The electrician began setting light poles on the concrete bases.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-18-21 Weekly Construction Update
Work this week: The contractor continued site grading and the first concrete pour was completed for the new walkways in the campus quad area.
Download PDF →North County Campus Parking Lot 10 and Site Improvements – 06-11-21 Weekly Construction Update
Work this week: The contractor started base placement and compaction work, along with formwork and reinforcing steel placement for the new walkways in the courtyard. Concrete is scheduled to follow. Rough grading of the site is ongoing.