NCC Parking Lot 10 & Site Improvements – 03-19-21 Weekly Construction Update
Work this week: The landscape contractor began planting trees. The demolition began on the former ECE play area. Modular buildings are being hauled off to prepare for the Phase 2 quad build out.
Download PDF →NCC Parking Lot 10 & Site Improvements – 03-12-21 Weekly Construction Update
Work this week: Circuiting was coordinated for the new light poles. Power and Data stations were placed at the locations of the future bus shelters.
Download PDF →NCC Parking Lot 10 & Site Improvements – 03-05-21 Weekly Construction Update
Work this week: Stripping work for the right turn lane leading to the drive aisle entrance was completed. The electrician installed uplights in the planter areas.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-26-21 Weekly Construction Update
Work this week: The contractor placed their second lift of asphalt in the traffic areas.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-19-21 Weekly Construction Update
Work this week: Landscaping contractor began trenching and installing irrigation lines.
Download PDF →NCC Parking Lot 10 & Site Improvements – 02-05-21 Weekly Construction Update
Work this week: New pedestrian flat work was poured at the walkway connecting Parking Lot 10 to the Campus Center. The second lift of asphalt paving is scheduled for next week.
Download PDF →February 2021 Monthly Project Update
Monthly status update on all existing Measure L projects.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-22-21 Weekly Construction Update
Work this week: New concrete was poured at the front of the Campus Center. Additional concrete was poured at the front drive aisle entrance off Buena Vista Drive.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-15-21 Weekly Construction Update
Work this week: New concrete was poured at the front of the Campus Center. New curb, gutter, and accessible pathways were also poured at the entrance to Parking Lot 11.
Download PDF →NCC Parking Lot 10 & Site Improvements – 01-08-21 Weekly Construction Update
Work this week: The first lift of asphalt was placed in Parking Lot 10. Additional concrete was poured around the Parking Lot.
Download PDF →