District-Wide Upgrades – Primary Electrical – 08-23-19 Weekly Construction Update
Work This Week: The 12KV primary contractor has been locating conduit ducts and other infrastructure...
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 08-09-19 Weekly Construction Update
Work This Week: The flooring contractor has completed the finish coat on the flooring and will begin floor penetrations for electrical outlets and volleyball posts...
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 07-19-19 Weekly Construction Update
Work This Week: The flooring contractor has completed installation of the flooring. It has been sanded, sealed, and finished behind the bleachers...
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 07-12-19 Weekly Construction Update
Work This Week: The flooring contractor has completed the install of the sub-floor behind the bleachers and has started install of floor paneling behind the bleachers...
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 07-05-19 Weekly Construction Update
Work This Week: The flooring contractor has finished the installation of the flooring panels from bleacher to bleacher and has moved the bleachers away from the walls to demo behind the bleachers...
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 06-14-19 Weekly Construction Update
Work This Week: The flooring contractor has finished installing the sub-floor and began installing new flooring panels...
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 06-07-19 Weekly Construction Update
Work This Week: The flooring contractor finished the demolition of the existing floor and began to install the sub floor.
Download PDF →District-Wide Upgrades – Gym Floor Replacement – 05-31-19 Weekly Construction Update
Work This Week: The contractor is removing the existing gym floor...