NCC Parking Lot 10 & Site Improvements – 11-20-20 Weekly Construction Update
November 20, 2020 · NCC Parking Lot 10 and Monument Sign, North County Sitework
Work this week: Installation of site lighting continued, with conduit being run and reinforcing steel being placed for the light pole bases. A large portion of the curb and gutter was poured at the drive aisle entry and the drop off entry loop.