Technology Upgrades Project – Athletics Fields – 02-08-19 Weekly Construction Update
February 8, 2019 · Construction Updates, SLO 1000 Complex Renovations, Technology Upgrades 2nd
Work this week: The electrical contractor began boring underground conduit from Bldg. 1700 to the softball fields and removing existing data drops, data cabling, and IDF rack in Bldg. 1700…
Download PDF →