Aquatics Center and 1000 Complex ADA Upgrades Project – 10-26-18 Weekly Construction Update
October 26, 2018 · Construction Updates, SLO 1000 Complex Renovations, Upgrades - Aquatic Center
Construction crews completed the majority of the competition pool wall reinforcement. Installation of the lights in the teaching pool began, and excavation of the teaching pool surge tank is complete. Punch list for buildings 1000 & 1300 is near completion.
Download PDF →