4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 12-23-22 Weekly Construction Update
December 23, 2022 · District Wide Upgrades 2nd
Work this week: Contractor has substantially completed 6100 restrooms and is preparing for punch walk next week. Tile is in progress at 5100, and drywall/sheetrock has been hung in 4300.