4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 11-11-22 Weekly Construction Update
November 11, 2022 · District Wide Upgrades 2nd
Work this week: Contractor installed restroom accessories in Building 4200 and 4600. Tile work in Building 4100 restrooms was completed. Framing work in Building 6100, remains ongoing.