4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-06-23 Weekly Construction Update
January 6, 2023 · District Wide Upgrades 2nd
Work this week: Contractor has substantially completed 6100 restrooms, and punch walk has been completed. Tile is now complete at 5100, and drywall/sheetrock has been hung in 4300. Ceilings have been painted and floors floated. Demolition at 6200, is complete. Underground plumbing is currently in progress.